Pipe A can fill a tank in 5 hours. Pipe B can empty it in 12 hours. If both pipes are opened together, how much time will it take to fill the tank?
Pipe A can fill a tank in 5 hours. Pipe B can empty it in 12 hours. If both pipes are opened together, how much time will it take to fill the tank?
पाइप A एक टैंक को 5 घंटे में भर सकता है। पाइप B इसे 12 घंटे में खाली कर सकता हैं। यदि दोंनो पाइप एक साथ खोले जाते हैं, तो टैंक को भरने में कितना समय लगेगा?
Detailed Solution & Logic
\(8\frac{4}{7}\) hours/\(8\frac{4}{7}\)घंटे
Given:
Rate of Pipe A = $ \frac{1}{5} $ tank/hour
Rate of Pipe B = $\frac{1}{12}$ tank/hour (emptying)
Net rate when both are open
= $ \frac{1}{5} - \frac{1}{12} $
= $ \frac{12-5}{60} = \frac{7}{60}$ tank/hour
Time required
= \(\frac{1}{7/60} = \frac{60}{7} = 8\frac{4}{7}\) hours
\(8\frac{4}{7} \)hours
Similar Practice Questions
Pipe P can fill \(\frac {3}{4}\) part of a tank in 27 hours, and pipe Q can fill \(\frac{2}{3}\) part of the same tank in 12 hours.
Pipe P can fill \(\frac {3}{4}\) part of a tank in 27 hours, and pipe...
A work can be finished in a day by 20 men
A work can be finished in a day by 20 men, or by 30 women,...
A, B and C together can complete a certain work in 40 days.
A, B and C together can complete a certain work in 40 days. B and...
Avi can finish a piece of work in 6 days, Avni can finish it in 8 days, Aarti can do it in 12 days and Reeta can do it in 16 days.
Avi can finish a piece of work in 6 days, Avni can finish it in...
Pipe P can fill 5/9 of a tank in 25 hours, and pipe Q can fill 8/9 of the same tank in 24 hours. Pipes P and Q are opened together for 3 hours and then closed. After that, only pipe R is opened, which can empty the tank in 8 hours. If pipes P, Q, and R are all opened together, how much time will it take to fill the empty tank?
Pipe P can fill 5/9 of a tank in 25 hours, and pipe Q can...
P can do a piece of work in 40 days. He worked on it for 10 days and then Q finished the work in 30 days. In how many days can P and Q together finish the work?
P can do a piece of work in 40 days. He worked on it for...
M and N can do a price of work in 16 days and O can do it in 48 days. In how many days will M, N, and O do this work together?
M and N can do a price of work in 16 days and O can...