Time and Work Questions with Solutions PDF for free download. Previous year SSC CGL, CHSL, Bank competitive Exams Quantitative Aptitude solved MCQs with short trick and explanation for preparation of upcoming exams.
Basic Concept of Time and Work
A and B can do a given piece of work in 8 days, B and C can do the same work in 12 days and A, B, C complete it in 6 days. The number of days required to finish the work by A and C is
Question Based on Where Worker Leaves or Joins
A, B and C can do a piece of work in 24, 30 and 40 days respectively. They began the work together but C left 4 days before completion of the work. In how many days was the work done?
Friction of Work
4 men and 6 women complete a work in 8 days. 2 men and 9 women also complete in 8 days in which, the number of days in which 18 women complete the work is
Efficiency of Worker
Pratibha is thrice as efficient as Sonia and is therefore able to finish a piece of work in 60 days less than Sonia. Pratibha and Sonia can individually complete the work respectively in
Based on Formula
If 4 men or 8 women can do a piece of work in 15 days, in how many days can 6 men and 12 women do the same piece of work?
Work and Wages
Three persons undertake to complete a piece of work for ` 1200. The first person can complete the work in 8 days, second person in 12 days and third person in 16 days. They complete the work with the help of a fourth person in 3 days. What does the fourth person get?
Download : Time and Work Questions with Solutions PDF
Name : SSC Mathematics Previous Year Solved Paper
Topic : Time and Work
Medium : English
Number of pages : 45
Free download the Time and Work Questions with short trick and Solutions from below link: