Time and Work Questions in English with Solution

Time and Work Questions in English with Answer and Solution – Free online practice Mock Test for Competitive Exams. All type Objective PSQ MCQs from SSC CGL, CHSL, CPO, GD examinations.

Quiz : Maths – Time and Work
Medium : English
Display of Solution immediately
Full Result on Summit / Finish of Test

 

Results

#1. Three men can complete a piece of work in 6 days. Two days after they started the work, 3 more men joined them. How many days will they take to complete the remaining work?

#2. If 20 women can lay a road of length 100 m 10 days. Then 10 women can lay the same road of length 50 m in :

#3. A man, a woman and a boy can together complete a piece of work in 3 days. If a man alone can do it in 6 days and a boy alone in 18 days, how long will a woman alone take to complete the work?

#4. 2 men and 1 woman together can complete a piece of work in 14 days, while 4 women and 2 men together can do it in 8 days. If a man gets Rs 600 per day, how much should a woman get per day?

#5. 2 men and 1 woman can complete a piece of work in 14 days while 4 women and 2 men can do the same work in 8 days. If a man gets Rs 180 per day, then what amount will a woman get per day?




#6. 8 workers can build a wall 18 m long, 2 m broad and 12 m high in 10 days, working 9 hours a day. Find how many workers will be able to build a wall 32 m long, 3 m broad and 9 m high in 8 days working 6 hours a day ?

#7. A man and a boy received Rs 800 as wages for 5 days for the work they did together. The man’s efficiency in the work was three times that of the boy. What are the daily wages of the boy ?

#8. A and B together can do a piece of work in 6 days. If A can alone do the work in 18 days, then the number of days required for B to finish the work is :

#9. 16 men are able to complete a piece of work in 12 days working 14 hours a day. How long will 28 men, working 12 hours a day, take to complete the work?

#10. A takes three times as long as B and C together to do a job. B takes four times as long as A and C together to do the work. If all the three, working together can complete the job in 24 days, then the number of days, A alone will take to finish the job is




#11. A and B can do a work in 12 days, B and C in 15 days and C and A in 20 days. If A, B and C work together, they will complete the work in

#12. If A and B together can finish a piece of work in 20 days, B and C in 10 days and C and A in 12 days, then A, B and C jointly can finish the same work in :

#13. A and B can complete a piece of work in 8 days, B and C can do it in 12 days, C and A can do it in 8 days. A, B and C together can complete it in :

#14. A group of workers can complete a piece of work in 50 days, when they are working individually. On the first day one person works, on the second day another person joins him, on the third day one more person joins them and this process continues till the work is completed. How many approximate days are needed to complete the work?

#15. A certain number of men can do a work in 40 days. If there were 8 men more, it could be finished in 10 days less. How many men were there initially?




#16. A, B and C can do a piece of work in 24, 30 and 40 days respectively. They began the work together but C left 4 days before completion of the work. In how many days was the work done ?

#17. A and B can together finish a work in 30 days. They worked at it for 20 days and then B left. The remaining work was done by A alone in 20 more days A alone can finish the work in :

#18. A, B and C can do a piece of work in 30, 20 and 10 days respectively. A is assisted by B on one day and by C on the next day, alternately. How long would the work take to finish?

#19. A and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after sometime and B completed the remaining work in 17 days. After how many days did A leave?

#20. A man is twice as fast as a woman and a woman is twice as fast as a boy in doing a work. If all of them, a man, a woman and a boy can finish the work in 7 days, in how many days a boy will do it alone?




#21. A man, a woman and a boy together finish a piece of work in 6 days. If a man and a woman can do the same work in 10 and 24 days respectively then the number of days taken by a boy to finish the work is :

#22. One man or two women or three boys can do a piece of work in 88 days. One man, one women and one boy will do it in :

#23. If 12 men working 8 hours a day complete the work in 10 days, how long would 16 men working 7\frac12 hours a day take to complete the same work?

#24. If 12 men working 8 hours a day complete the work in 10 days, how long would 16 men working 7\frac12 hours a day take to complete the same work?

#25. A can cultivate \frac25 th of a land in 6 days and B can cultivate \frac13 rd of the same land in 10 days. Working together A and B can cultivate \frac45 th of the land in :




#26. A can cultivate \frac25 th of a land in 6 days and B can cultivate \frac13 rd of the same land in 10 days. Working together A and B can cultivate \frac45 th of the land in :

#27. If 28 men complete \frac78 of a piece of work in a week, then the number of men, who must be engaged to get the remaining work completed in another week, is :

#28. If 28 men complete \frac78 of a piece of work in a week, then the number of men, who must be engaged to get the remaining work completed in another week, is :

#29. Sunil completes a work in 4 days, whereas Dinesh completes the work in 6 days. Ramesh works 1\frac1 2 times as fast as Sunil. The three together can complete the work in :

#30. Sunil completes a work in 4 days, whereas Dinesh completes the work in 6 days. Ramesh works 1\frac1 2 times as fast as Sunil. The three together can complete the work in :




#31. A can do a piece of work in 6 days. B is 25% more efficient than A. How long would B alone take to finish this work?

#32. A group of 75 men are employed to lay down a railway line in 3 months. Due to certain emergency conditions, the work was to be finished in 18 days. How many more men should be employed to complete the work in the desired time ?

#33. If 80 persons can finish a work within 16 days by working 6 hours a day, the number of hours a day, should 64 persons work to finish that very job within 15 days is :

#34. Suppose that ‘x’ number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is :

#35. A can do a piece of work in 16 days and B in 24 days. They take the help of C and they together finish the work in 6 days. If the total remuneration for the work is Rs 400. The amount (in Rs ) each will receive, in proportion, to do the work is :




#36. Every Sunday, Gin jogs 3 miles. For rest of the week, each day he jogs 1 mile more than the previous day. How many miles Gin jogs in 2 weeks?